Serra de l'Ebre
Needs attentionCatalonia · Wind · 57 MW installed · 5 technicians · manager Mariano O'Hara
13.4 MW
24 %
275 MWh
96.6 %
9 / 13
5
Wind
8.6 m/s S
Irradiance
0 W/m²
Temperature
17.2 °C
Cloud cover
30 %
Conditions
Sunny intervals
Substation
Ascó SE 400 kV
Voltage
400.2 kV
Frequency
50.022 Hz
Power factor
0.987
Curtailment
8 %
Day-ahead price
100.09 €/MWh
Assets
13 assets on site. Open one for its live 3D view.
Wind turbine
WTG-03
Siemens Gamesa SG 5.0-145 · 6.2 MW
Output
4.17 MW
Today
28.4 MWh
Wind
10.7 m/s
Wind turbine
WTG-04
Siemens Gamesa SG 5.0-145 · 5.0 MW
Output
0.45 MW
Today
28.9 MWh
Wind
6.6 m/s
Wind turbine
WTG-05
Siemens Gamesa SG 6.6-170 · 6.2 MW
Output
0.00 MW
Today
13.5 MWh
Wind
8.6 m/s
Wind turbine
WTG-07
Siemens Gamesa SG 5.0-145 · 5.0 MW
Output
0.00 MW
Today
25.6 MWh
Wind
9.2 m/s
Wind turbine
WTG-09
Siemens Gamesa SG 6.6-170 · 6.2 MW
Output
1.11 MW
Today
22.6 MWh
Wind
9.4 m/s
Wind turbine
WTG-10
Siemens Gamesa SG 6.6-170 · 4.2 MW
Output
0.60 MW
Today
30.0 MWh
Wind
7.4 m/s
Inverter skid
INV-01
Sungrow SG3125HV-MV · 4.6 MVA
Output
0.51 MW
Today
30.6 MWh
Availability
99.5 %
Inverter skid
INV-02
SMA Sunny Central 4600 UP · 3.1 MVA
Output
2.11 MW
Today
16.4 MWh
Availability
96.3 %