Monte Cañón

Degraded

Galicia · Wind · 74 MW installed · 6 technicians · manager Kiarra Swaniawski

Output now

25.1 MW

Load factor

34 %

Energy today

658 MWh

Availability

96.9 %

Producing

12 / 16

Open alarms

4

Generation
Last 12 hours
Wind, solar and battery power at the point of interconnection. A charging battery shows below zero.
Conditions
Resource and grid

Wind

9.6 m/s SE

Irradiance

0 W/m²

Temperature

17.2 °C

Cloud cover

15 %

Conditions

Sunny intervals

Substation

Mesón SE 220 kV

Voltage

220.0 kV

Frequency

50.004 Hz

Power factor

0.987

Curtailment

19 %

Day-ahead price

100.58 €/MWh

Assets

16 assets on site. Open one for its live 3D view.

Power flow

Wind turbine

WTG-01

Siemens Gamesa SG 5.0-145 · 6.2 MW

Producing
55%

Output

3.41 MW

Today

53.6 MWh

Wind

10.4 m/s

Wind turbine

WTG-02

Siemens Gamesa SG 6.6-170 · 4.2 MW

Producing
19%

Output

0.78 MW

Today

40.6 MWh

Wind

7.7 m/s

Wind turbine

WTG-03

Nordex N149/4.0-4.5 · 6.2 MW

Producing
86%

Output

5.33 MW

Today

67.5 MWh

Wind

11.7 m/s

Wind turbine

WTG-04

Siemens Gamesa SG 5.0-145 · 5.0 MW

Producing
2%

Output

0.09 MW

Today

42.9 MWh

Wind

5.0 m/s

Wind turbine

WTG-05

Nordex N149/4.0-4.5 · 6.2 MW

Producing
21%

Output

1.29 MW

Today

48.8 MWh

Wind

8.1 m/s

Wind turbine

WTG-06

Vestas V162-6.2 · 5.0 MW

Producing
7%

Output

0.36 MW

Today

44.7 MWh

Wind

6.4 m/s

Wind turbine

WTG-07

Vestas V162-6.2 · 4.2 MW

Curtailed
5%

Output

0.21 MW

Today

19.2 MWh

Wind

6.8 m/s

Wind turbine

WTG-08

Nordex N149/4.0-4.5 · 6.2 MW

Producing
31%

Output

1.94 MW

Today

67.2 MWh

Wind

8.7 m/s

Wind turbine

WTG-09

Vestas V150-4.2 · 6.2 MW

Producing
98%

Output

6.09 MW

Today

67.6 MWh

Wind

12.0 m/s

Wind turbine

WTG-10

Siemens Gamesa SG 5.0-145 · 6.2 MW

Producing
38%

Output

2.32 MW

Today

54.4 MWh

Wind

9.4 m/s

Wind turbine

WTG-11

Siemens Gamesa SG 6.6-170 · 5.0 MW

Producing
54%

Output

2.72 MW

Today

53.1 MWh

Wind

10.1 m/s

Wind turbine

WTG-12

Vestas V162-6.2 · 5.0 MW

Standby
0%

Output

0.00 MW

Today

41.4 MWh

Wind

11.3 m/s

Wind turbine

WTG-13

Siemens Gamesa SG 5.0-145 · 4.2 MW

Producing
2%

Output

0.07 MW

Today

32.6 MWh

Wind

4.9 m/s

Wind turbine

WTG-14

Vestas V150-4.2 · 4.2 MW

Curtailed
12%

Output

0.51 MW

Today

24.6 MWh

Wind

8.4 m/s

Inverter skid

INV-01

SMA Sunny Central 4600 UP · 5.0 MVA

Producing
95%

Output

4.75 MW

Today

39.0 MWh

Availability

99.6 %

Inverter skid

INV-02

Sungrow SG3125HV-MV · 5.0 MVA

Curtailed
43%

Output

2.14 MW

Today

26.2 MWh

Availability

94.2 %

Alarms
Site alarms
Most recent events from this site's assets.

Blade ice detected

WTG-02· 10-28 16:03
Medium

IGBT temperature high

INV-02· 10-28 09:12
Low

Pitch system hydraulic pressure low

WTG-05· 10-28 01:46
Low

Yaw misalignment above limit

WTG-07· 10-27 21:27
Low